Cost Breakdown
Name/Model: Black Knight BL-9-WB-KNT
Technology: Inner Sphere
Tonnage: 75
Configuration: Biped BattleMech
===================================================================================================================
Structural Cost
-------------------------------------------------------------------------------------------------------------------
Armor (Standard): (216 pts) 13.5 x 10,000 135,000.00
Internal Structure (Standard): 75 x 400 x 1 (+) 30,000.00 = 165,000.00
Myomer (Standard): 75 x 2,000 (+) 150,000.00 = 315,000.00
Engine (XL): (20,000 x 300 x 75) / 75 (+) 6,000,000.00 = 6,315,000.00
Gyro (Standard): 3.0 x 300,000 (+) 900,000.00 = 7,215,000.00
Cockpit (Standard): 200,000 (+) 200,000.00 = 7,415,000.00
Life Support: 50,000 (+) 50,000.00 = 7,465,000.00
Sensors: 75 x 2,000 (+) 150,000.00 = 7,615,000.00
Heat Sinks (Double): 16 x 6,000 (+) 96,000.00 = 7,711,000.00
Arm Actuators: 75 x ((100 x 2) + (50 x 2) + (80 x 2)) (+) 34,500.00 = 7,745,500.00
Leg Actuators: 75 x ((150 x 2) + (80 x 2) + (120 x 2)) (+) 52,500.00 = 7,798,000.00
-------------------------------------------------------------------------------------------------------------------
Total Structural Cost: 7,798,000.00
===================================================================================================================
Weapons and Equipment Cost
-------------------------------------------------------------------------------------------------------------------
ER PPC 300,000 300,000.00
Hatchet 5 x 5,000 (+) 25,000.00 = 325,000.00
Improved C3 Computer 750,000 (+) 750,000.00 = 1,075,000.00
Large Laser 100,000 (+) 100,000.00 = 1,175,000.00
Large Laser 100,000 (+) 100,000.00 = 1,275,000.00
Medium Pulse Laser 60,000 (+) 60,000.00 = 1,335,000.00
Medium Pulse Laser 60,000 (+) 60,000.00 = 1,395,000.00
Medium Pulse Laser 60,000 (+) 60,000.00 = 1,455,000.00
Medium Pulse Laser 60,000 (+) 60,000.00 = 1,515,000.00
-------------------------------------------------------------------------------------------------------------------
Total Weapons and Equipment Cost 1,515,000.00
===================================================================================================================
BattleMech Cost
-------------------------------------------------------------------------------------------------------------------
Structural Cost: 7,798,000.00
Weapons and Equipment Cost: (+) 1,515,000.00 = 9,313,000.00
BattleMech Cost Multiplier: 1 + (75 / 100) (*) 1.75 = 16,297,750.00
-------------------------------------------------------------------------------------------------------------------
Final BattleMech Cost 16,297,750.00
|